Delivered $16M of static and rotary shutdown work. Mechanical engineering support for rotating and static equipment, frames and skids.

I’m Abdullah Abdullah, P.Eng. (APEGA ID 209405), with 7+ years as a mechanical engineer. I’ve coordinated up to 60 contractors and scoped projects from $100K to $4M. My focus: SolidWorks models, fabrication drawings, FEA and equipment reviews for Alberta plants and engineering firms.

What I deliver

Practical engineering for plant owners and engineering firms in Alberta.

  • SolidWorks 3D models & drawings

    Parametric models and weldment frames for skids, supports and stands.

  • Fabrication packages

    GAs, cut lists, base plate and weld details.

  • As-built drawings

    After shutdowns and modifications, in SolidWorks or AutoCAD.

  • FEA & design checks

    Finite element analysis in SolidWorks for equipment design and modifications.

  • Rotating & static equipment reviews

    Pumps (API 610/676/685), exchangers, vessels; FFS to API 579.

  • Shutdown planning support

    Scopes, work packages, MRQs; HAZOP, RCA, PSSR and MOC.

Engineering services for clients begin once an APEGA Permit to Practice is issued. Until then, I welcome enquiries and scoping conversations.

How I solve problems

The same four steps behind $16M of static and rotary shutdown work.

  1. Understand the failure or need

    Plant tours, root cause analysis, and the HAZOP and MOC context.

  2. Model & analyse

    SolidWorks 3D and FEA, checked against API, ASME and ABSA requirements.

  3. Deliver fabrication-ready packages

    Drawings, cut lists, scopes and MRQs your team can build and buy from.

  4. Support execution

    Shutdown planning, schedules and QA/QC, coordinating up to 60 contractors through commissioning.

Have a frame, skid or retrofit?

Tell me about it in about two minutes.

Projects: problem, fix, result

Every project below is from my own work, grouped by capability.

Rotating equipment

  • Problem
    Kiln trunnions suffered a breakdown failure.
    What I did
    Replaced all of the kiln’s trunnions, then aligned the incinerator.
    Result
    $400K · done to preserve operations and asset health
  • Problem
    The facility’s main induced draft fan needed a complete overhaul.
    What I did
    Overhauled the casing, bearings and motor, then commissioned the fan.
    Result
    $500K · fan overhauled and commissioned
  • Problem
    Volatile organic waste fluids needed homogenizing in a tank.
    What I did
    Installed a tank agitator.
    Result
    $185K · agitator installed

Heat transfer & pressure equipment

  • Problem
    The facility’s air compressors needed cooling and piping work.
    What I did
    Delivered two fin-fan heat exchangers, a pump skid and piping for the air compressors.
    Result
    $800K static shutdown scope delivered
  • Problem
    Corrosive process fluids called for corrosion-resistant heat exchange.
    What I did
    Installed three titanium plate heat exchangers.
    Result
    $500K static shutdown scope delivered
  • Problem
    Static equipment had to meet company standards and ABSA requirements.
    What I did
    Designed, sized and purchased shell and tube heat exchangers, pressure vessels, condenser pots and chemical dosing skids.
    Result
    Equipment specified to standard and ABSA requirements

Materials handling

  • Problem
    The main shredder had to handle solid wastes, light metals and concrete.
    What I did
    Upgraded the main shredder.
    Result
    $900K rotary shutdown scope delivered
  • Problem
    The incinerator’s feed system needed an upgrade.
    What I did
    Upgraded the entire hydraulic feed system: gates, rams and conveyors.
    Result
    $300K rotary shutdown scope delivered
  • Problem
    An elevator critical to moving barrels and drums for incineration needed work.
    What I did
    Executed its mechanical overhaul.
    Result
    $70K · critical elevator overhauled

FEA & fitness-for-service

  • Problem
    Pressure vessels needed integrity checks.
    What I did
    Ran FEA in SolidWorks and fitness-for-service analysis in INSPECT to API 579 and ASME VIII/IX.
    Result
    FEA and fitness-for-service analysis delivered
  • Problem
    Rotating equipment had to meet API 610, 685 and 676.
    What I did
    Designed, sized and purchased canned hermetic, 13-stage VS6/VS7, centrifugal and PD dosing pumps.
    Result
    Pumps specified to API standards
  • Problem
    A plant needed to keep running until its next outage.
    What I did
    Provided plant support and designed modifications.
    Result
    Modifications designed to sustain operations to the next outage

Shutdown execution

  • Problem
    Five critical-path shutdown projects had to improve production efficiency and minimize downtime.
    What I did
    Conceptualized, planned, executed and commissioned them, running schedules, budgets and reporting for crews of up to 42.
    Result
    $3.3M across five critical-path shutdowns
  • Problem
    Combustion air flow needed better monitoring and control.
    What I did
    Installed venturi meters (phase 1).
    Result
    $160K · phase 1 delivered
  • Problem
    Power distribution to critical plant equipment needed inspection.
    What I did
    Inspected and maintained MCCs and switchgear.
    Result
    $53K · inspection and PM completed

Summaries use only publicly shared experience, never confidential information. Values are project values as stated in my work history.

Experience

  • Senior Reliability Engineer (current)Jan 2025 – present
  • Engineering Project Lead · industrial waste treatment facility, Western CanadaNov 2018 – Nov 2025
  • Mechanical Design Engineer · contract assignment, global chemical manufacturerSep – Dec 2023
  • Engineering Project Lead (co-op) · industrial treatment facility, Western CanadaMay – Sep 2018
  • Research Engineer (co-op) · national research laboratoryMay – Sep 2016

Client and employer names withheld for confidentiality; references available on request.

Education

  • B.Sc. Mechanical EngineeringUniversity of Alberta
  • M.Eng.University of Alberta

Codes, standards & tools

  • API 610 / 676 / 685
  • API 579 FFS
  • ASME VIII / IX
  • ABSA
  • SolidWorks (incl. FEA)
  • AutoCAD
  • INSPECT
  • MATLAB / R
Start a scoping conversation